ARTICLE
8 November 2023

Analysis: Limits of an Arbitration Award And Liquidated Damages

SA
Shardul Amarchand Mangaldas & Co
Contributor
Shardul Amarchand Mangaldas & Co founded on a century of legal achievements, is one of India’s leading full-service law firms. The Firm’s mission is to enable business by providing solutions as trusted advisers through excellence, responsiveness, innovation and collaboration. SAM & Co is known globally for its exceptional practices in mergers & acquisitions, private equity, competition law, insolvency & bankruptcy, dispute resolution, capital markets, banking & finance and projects & infrastructure.
These legal components are critical in resolving disputes and ensuring fairness and equity in contractual relationships.
India Litigation, Mediation & Arbitration
To print this article, all you need is to be registered or login on Mondaq.com.

In the world of commercial contracts and disputes, two legal aspects often take centre stage: Section 34 of The Arbitration and Conciliation Act, 1996 (A&C Act), and the concept of liquidated damages. These legal components are critical in resolving disputes and ensuring fairness and equity in contractual relationships.

This article analyses the critical aspects of Section 34 of the A&C Act, and the concept of liquidated damages under the Contract Act stemming from the order passed by the High Court of Delhi in the case of Vinod Seth (deceased) through legal heirs v. Sudershan Kumar Bhayana(deceased) through legal heirs and Kiran Bhayana (Owners) (deceased) through legal heirs.

Background:

The case revolved around a Collaboration Agreement signed in 2010(Agreement) between property owners Sudershan Kumar Bhayana and Kiran Bhayana (Owners) and builder Vinod Seth (Builder). The Builder was responsible for demolishing and reconstructing a property within a specified time frame. However, disputes led to the termination of the Agreement in November 2011.

Arbitration proceedings:

The Builder initiated legal proceedings under Section 9 of the A&C Act, leading to both parties agreeing to arbitration. The Owners claimed damages due to construction delays, alleging a breach of the Agreement by the Builder.

In response, the Builder filed a counterclaim seeking monetary relief among other things. The arbitral tribunal partially allowed the Builder's counterclaim, awarding lower monetary amount, while reducing the Owners' claim.

Award challenged:

The Owners accepted the award. The Builder however filed an application under Section 34 of the A& C Act, challenging the arbitral tribunal's decision. This is the crux of the issue.

Section 34: limits and interpretations:

Section 34 of the A&C Actsets out specific grounds on which an arbitral award can be challenged. It does not grant the power to the Court to modify an award. This interpretation aligns with the A&C Act's foundation on the UNCITRAL Model Law, emphasizing minimal judicial interference with awards. The Single Judge upheld the award but modified the damages computation.

Decoding liquidated damages:

Liquidated damages are a contractual provision that specifies a predetermined amount to be paid by one party to another in the event of a breach of contract. This predetermined amount serves as compensation for the harm or loss incurred due to the breach. The fundamental principle behind liquidated damages is that parties agree upon a reasonable estimate of potential damages in advance, thus avoiding the need for protracted and uncertain litigation to determine the actual damages.

The core of the argument revolves around applicability of a predetermined per day penalty amount in the Agreement. This provision states that if there are delays in construction, predetermined amount per day will be applied for construction delays. This clause, raises the following key issues:

i. Evidence of damages:

The Builder argued that the Owners had not provided enough evidence to support their damage claims. This is a crucial aspect of liquidated damages. Courts have consistently held that damages cannot be awarded based solely on a penalty clause without supporting evidence.

ii. Period of damages:

The Agreement allowed for a total construction period of fourteen months, including a two-month grace period. After its termination in 2011, no further construction could occur. Therefore, the maximum delay period could not exceed the total construction period.

iii. Effect post termination:

Post termination of the Agreement, the enforcement mechanism defined in the penalty clause became irrelevant, as the Builder was no longer obligated to continue construction.

The judgment raises questions about whether it should be set aside based on the court's overreach into arbitration decisions. The Court's power under Section 34 of the A&C Act is limited to specific grounds, and it cannot replace the tribunal's decision.

Disposition of appeals:

Ultimately the award was set aside specifically the claims awarded to the Owners due to patent illegality.

Conclusion:

In the intricate realm of arbitration and contract law Section 34 of the A&C Act and liquidated damages are indispensable tools for ensuring fairness and accountability in contractual relationships. Section 34 provides a mechanism for reviewing arbitral awards, but it's crucial to understand its limitations – courts can only set aside awards on specific grounds and not modify the awards.

The concept of liquidated damages offers parties an efficient way to pre-determine compensation for breaches of contract. However, it's equally important for parties to keep in mind that such damages must be reasonable and based on genuine estimates of potential loss.

This judgement stresses the importance of these principles and their intersection in real-world contractual disputes. It highlights the importance of upholding these legal principles to ensure fairness and integrity of contractual agreements.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

ARTICLE
8 November 2023

Analysis: Limits of an Arbitration Award And Liquidated Damages

India Litigation, Mediation & Arbitration
Contributor
Shardul Amarchand Mangaldas & Co founded on a century of legal achievements, is one of India’s leading full-service law firms. The Firm’s mission is to enable business by providing solutions as trusted advisers through excellence, responsiveness, innovation and collaboration. SAM & Co is known globally for its exceptional practices in mergers & acquisitions, private equity, competition law, insolvency & bankruptcy, dispute resolution, capital markets, banking & finance and projects & infrastructure.
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More