Vincent Young is a true boutique construction, property + projects, employment + workplace relations firm. We are hands on. We manage every matter as if it were our own. We mix and match our lawyers and consultants to seamlessly produce cost effective, high quality work consistent with the client risk profile.
Contractors with defects claims against subcontractors often commence litigation prematurely to preserve their claims from being time-barred.
Australia Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

Price v Spoor [2021] HCA 20 (Price v Spoor)

Contractors with defects claims against subcontractors often commence litigation prematurely to preserve their claims from being time-barred. This occurs despite the costly nature of litigation and its potential to undermine settlement negotiations. The High Court case of Price v Spoor has confirmed that in some cases, standstill agreements may be used to suspend limitation periods from running during settlement negotiations.

What is a standstill agreement?

A standstill agreement involves a party making a claim (such as a contractor) agreeing to hold off initiating legal proceedings against the other party (such as a subcontractor). In return, the other party agrees to suspend the running of time during the limitation period in respect of the claim.

Price v Spoor

The use of a standstill agreement to suspend the running of time during the contractual limitation period was recognised in Price v Spoor, where the Court confirmed that parties may 'contract out' of some statutory limitation periods.

The Court's reasoning was that:

  1. contracting out of some statutory limitation periods is not contrary to public policy because the limitation period is not an automatic bar to proceedings but rather a defence for a defendant to raise individually; and
  2. parties have freedom of contract to waive the limitation defence unless this is expressly prohibited by, or contradicts the intention of, the relevant limitation statute.

Limitation periods of contractual and tortious claim may be waived

While Price v Spoor concerns the Limitation of Actions Act 1974 (QLD) in Queensland, the Court's reasoning could equally apply to the Limitation Act 1969 (NSW), which is the equivalent NSW legislation. Parties may be able to rely on a standstill agreement to suspend the limitation periods as set out in the Limitation Act 1969 (NSW) for contractual and tortious claims.

Where a standstill agreement may not apply

Despite the Court's determination in Price v Spoor, it is still risky to try to use a standstill to suspend the running of time during the limitation periods under the Home Building Act 1989 (NSW) (HBA) and Environmental Planning and Assessment Act 1979 (NSW) (EPAA) because the HBA and EPAA use stronger, mandatory language. For instance:

  1. section 18E(a) of the HBA states "Proceedings must be commenced before the end of the warranty period for the breach" (emphasis added); and
  2. section 6.20(1) of the EPAA states "A civil action for loss or damage arising out of or in connection with defective building work or defective subdivision work cannot be brought more than 10 years after the date of completion of the work. (emphasis added)"

Key Takeaways

Contractors approaching limitation periods for claims who are in negotiations may be able to use a standstill agreement to delay commencing litigation depending on the nature of their claims.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Standstill Agreements Pending Negotiations

Australia Real Estate and Construction

Contributor

Vincent Young is a true boutique construction, property + projects, employment + workplace relations firm. We are hands on. We manage every matter as if it were our own. We mix and match our lawyers and consultants to seamlessly produce cost effective, high quality work consistent with the client risk profile.
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More