31 October 2023

FERC Extends Order No. 2023 Interconnection Process Reform Compliance Deadlines

AG
Akin Gump Strauss Hauer & Feld LLP
Contributor
Akin is a law firm focused on providing extraordinary client service, a rewarding environment for our diverse workforce and exceptional legal representation irrespective of ability to pay. The deep transactional, litigation, regulatory and policy experience we bring to client engagements helps us craft innovative, effective solutions and strategies.
On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order1 that extended the deadline for electric transmission providers to comply with its Order No. 2023...
United States Energy and Natural Resources
To print this article, all you need is to be registered or login on Mondaq.com.

On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order1 that extended the deadline for electric transmission providers to comply with its Order No. 2023, "Improvements to Generator Interconnection Procedures and Agreements" (the Final Rule2). The new compliance filing deadline is Wednesday, April 3, 2024, or 210 calendar days from the Final Rule's publication in the Federal Register on September 6, 2023. The previous deadline had been December 5, 2023, or 90 days from the publication date. The revised deadline applies to "all transmission providers, except for those with wholesale distribution access tariffs," whose compliance filings are now due "within 90 calendar days of the date on which their relevant regional transmission organization or independent systems operator submits its compliance filing."3 FERC clarified that the Extension Order "does not change or modify any other determination or other deadlines established by Order No. 2023, including the deadline for eligibility for interconnection customers to opt to proceed with a transitional serial study (for those interconnection customers tendered a facilities study agreement) or transitional cluster study (for those interconnection customers assigned a queue position) or to withdraw their interconnection requests without penalty (i.e., 30 calendar days after the transmission provider submits its initial compliance filing)."4

Under the Final Rule, transmission providers must speed up the processing of requests in their interconnection queues, adopt a "first-ready, first-served" cluster study process and integrate technological advancements in generation and transmission into the interconnection process.

Footnotes

1. Improvements to Generator Interconnection Procs. & Agreements, 185 FERC ¶ 61,063 (2023) (Extension Order).

2. Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054 (2023).

3. Extension Order at PP 3, 9-10.

4. Id. at P 11.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

ARTICLE
31 October 2023

FERC Extends Order No. 2023 Interconnection Process Reform Compliance Deadlines

United States Energy and Natural Resources
Contributor
Akin is a law firm focused on providing extraordinary client service, a rewarding environment for our diverse workforce and exceptional legal representation irrespective of ability to pay. The deep transactional, litigation, regulatory and policy experience we bring to client engagements helps us craft innovative, effective solutions and strategies.
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More